Explore Pakistan's gridand test what's next
Wattlas puts the whole power system on one map. Build a plant. Push demand up somewhere. Watch the numbers move. It was made to answer the questions planners actually ask.
1,673MW
the grid could not deliver at 11pm on 20 June 2025, the busiest night of the year
Bigger than any power station in the country except Tarbela. Gone, every evening.
29,201MW
FY25 peak demand, at 23:00
measured
48,316MW
Generation capacity mapped
measured
1,658stations
Demand stations placed
measured + modelled
160districts
Demand modelled 11 years out
derived
Also here
Bijli Baba
Bill assistant
“Send me your bill. I will tell you where the money went.”
The rest of this site is about the national grid. Baba is about yours. Type the figures off your bill, or photograph it, and he works out where your units are going, what the next one costs you, and whether solar would pay.
Ask him something
Sample answers
One kilowatt-hour. An appliance rated at one kilowatt, running for one hour, uses one unit. The UNITS box on your bill is the number everything else is worked out from.
Six things it answers
Some of it is what already exists. The rest is what happens if you change it.
The grid, on a map
Every plant, every substation, every line. Coloured by what it burns and how much it carries.
Wired up properly
The high-voltage network is a real graph here, 66 kV through 500 kV. That includes the Matiari-to-Lahore HVDC link and everything the national backbone hangs off.
Break something and watch
Put up a solar farm. Shut a thermal plant. Crank demand in one province. The rest of the system reacts.
Forecasts you can argue with
Quantile forecasts with honest uncertainty bands, trained on ten years of measured Pakistani hourly demand and weather.
Where it gets tight
Find the transmission that runs hot, and how much storage it takes to firm up renewables when the reserve margin thins.
What the transition costs
Try a build-out. See what it does to reliability, to congestion, and to the emissions curve.
From raw records to an answer
Pull the records
Generation assets and the transmission network come out of open data and permissioned NTDC files, then get knitted into one national model.
Change something
Drop a new asset onto the grid, or move demand. The engine recomputes the provincial balances.
Read what happened
Before and after, on supply and on balance. Every estimate says what kind of number it is.
Go and break the grid
Open the map. Turn on the layers you want. Run a scenario and follow it from the provinces down to individual districts.
This is planning-grade, not a live feed. It runs on open data, permissioned NTDC records and a set of modelling assumptions. Estimates and forecasts are labelled as such wherever they appear.